Don’t rush the draft resource consent conditions
When draft resource consent conditions land in your inbox, the natural reaction is to want them signed off straight away. Clients are often anxious to get the final approval, and a few more days of waiting can feel like a few more days too many.
Resist the urge. Those conditions decide how much your project will cost and how long it will take, so they deserve a proper read before anything is confirmed.
Councils don’t have to send drafts
Councils aren’t obliged to issue draft conditions. Most do so willingly, to give you the chance to pick up anything obvious that was missed. It has become a standard part of the process, and it gives you room to question what is unclear and to suggest improvements that suit both sides.
Every condition has a price tag
Any condition that requires physical work adds cost and time. A drainage connection renewal, a trench in the road and additional testing for confirmation are typical examples. Each one has a knock-on effect for your budget and your programme, and on a subdivision or development those effects add up quickly.
The reverse is also true. If you can get a number of conditions removed or reworded, you save both time and money.
Slow down now, save time later
Issuing the decision quickly gets you started sooner. But the time spent refining the draft conditions comes back to you near completion, when unclear or unnecessary conditions would otherwise hold up sign-off.
What to do when the draft arrives
- Read every condition against your timeframes, objectives and intended outcomes.
- Flag any condition that is unclear, unnecessary or more costly than the outcome justifies.
- Talk to us before replying to Council, so we can raise the right issues and propose workable alternatives.
A day or two spent debating the draft conditions will often prevent delays and save you significant costs down the track.