Nine Townhouses to Seven – and a $290,000 Development Contribution Surprise
A client came to us with a problem a lot of developers are facing right now: a Resource Consent that no longer matches the market.
They held consent for nine townhouses across three blocks. Good scheme, solid design. But the market has shifted since then, and buyers aren’t chasing multi-unit blocks the way they were. They want their own front door, their own patch of ground, a carpark that’s actually theirs.
So we went back to the drawing board and reworked the site into seven detached townhouses with garages. More flexible for the client too: get titles and sell the sites individually, or build one at a time as sales allow, rather than committing to three blocks at once.
On paper, it’s a better product for today’s buyer. Fewer units, same land, same infrastructure load. You’d assume the numbers would move in the client’s favour.
They didn’t.
The DC recalculation nobody budgets for
Their current Development Contributions, based on the 2022 charging schedule that applied when the original consent was assessed, sit at $38,388 for the nine townhouses.
Change the consent to seven detached units, and Council reassesses under the current schedule. The new figure: $327,528.
Same site. Same three-waters connections. Two fewer units. An increase of close to $290,000.
That’s not a rounding error in a feasibility study. That’s the difference between a deal that stacks up and one that doesn’t.
Why this catches developers out
A change of consent isn’t a tweak. Council treats it as a fresh assessment against whatever charging schedule is current on the day you lodge, not the one that applied when your original consent went through. If your DCs were locked in years ago under an older schedule, any amendment resets that clock.
Fewer dwellings doesn’t mean a lower bill either. Development Contributions are calculated against infrastructure demand, not simply a headcount of units, and the methodology behind that calculation has moved.
The takeaway
If you’re sitting on a consent that predates the current market and you’re thinking about reworking it, run the Development Contributions numbers before you fall in love with the redesign. A better product on paper can still be a worse deal on the bottom line if the council’s charging schedule has moved since your original consent was granted.